PRE-CONSTRUCTION ACTIVITIES

Download the Lessonotes Mobile Ghana app for faster lesson access on Android and iPhone.

Subject: Applied Technology

Class: SHS 1

Term: 1st Term

Week: 18

Grade code: 1.2.1.LI.3

Strand code: 2

Sub-strand code: 1

Content standard code: 1.2.1.CS.2

Indicator code: 1.2.1.LI.3

Theme: BUILDING CONSTRUCTION TECHNOLOGY

Subtheme: PRE-CONSTRUCTION ACTIVITIES

Lesson Video

This page supports the lesson note with a companion video and a short classroom-ready summary.

For class groups and homework, share this lesson page so learners also get the summary, objectives, and full lesson context.

Performance objectives

Lesson summary

Imagine our school decides to build a new library. Before the first block is laid or the first bag of cement is mixed, the contractor must plan the entire construction site. Where will the workers rest and eat? Where will the expensive cement and iron rods be stored safely? Where will the site manager have his office? How can we make sure a tipper truck delivering sand doesn't run into a worker carrying wood? This planning is called Site Layout and Organisation, and it is a critical pre-construction activity. A well-organised site is like a well-organised kitchen – it is safer, faster, and produces better results.

Lesson notes

A. What are Temporal (Temporary) Site Items?

These are structures, facilities, and services that are set up at the beginning of a construction project and are usually removed once the project is complete. They are not part of the final building but are essential for supporting the construction work. Temporal Structures: These are temporary buildings. Site Office: The administrative hub for the site manager, engineers, and supervisors. It's where plans are kept, meetings are held, and records are managed. Stores / Warehouse: A secure, covered place to store valuable or weather-sensitive materials like bags of cement, electrical wires, and tools. Workshop: An area for fabricating or repairing components, such as a carpentry workshop for making formwork or a metalwork area for cutting and bending reinforcement bars. Canteen / Eating Area: A designated place for workers to have their meals. Security Post: A small shelter, usually at the main gate, for security personnel to monitor who enters and leaves the site. Welfare Facilities: These are for the health, comfort, and well-being of the workers. Toilets / Sanitary Facilities: Essential for hygiene (e.g., KVIP, mobile toilets). Changing Rooms / Lockers: A place for workers to change into their work clothes and store personal belongings. First Aid Station: A clearly marked location with a first aid kit and, on larger sites, a trained first aid attendant. Drinking Water Supply: A source of clean drinking water. Temporal Services: These are essential utilities required for the construction work. Water Supply: Needed for mixing concrete and mortar, cleaning, and for workers' use. Often from a Ghana Water Company connection or a temporary water tanker/polytank. Electricity Supply: Needed to power tools (drills, saws), lighting, and the site office. Often from the ECG grid or a generator. Access Roads: Temporary roads within the site for vehicles like tipper trucks and concrete mixers to move around without getting stuck in mud. Plant and Equipment: Heavy machinery used for construction. Excavator: For digging foundations and clearing the site. Concrete Mixer: For mixing cement, sand, aggregate, and water. Crane: For lifting heavy materials on multi-storey projects. Tipper Trucks: For delivering materials like sand and stones. B. The Main Tool: The Site Layout Plan

You cannot just place these items anywhere you like. The location of every single item is specified on a drawing called a Site Layout Plan.

A Site Layout Plan is a map or a bird's-eye view drawing of the entire construction site. It shows the boundary of the site, the location of the permanent building being constructed, and the planned positions of all the temporal structures, services, facilities, and material storage areas.